The previously planned overnight closures between 29 August and 2 September will no longer be required. However, to allow specific stages of the repair work to proceed safely, full overnight closures of the A96 at the bridge will take place on the following dates:
  • Thursday 10 September
  • Tuesday 15 September
  • Monday 21 September
  • Thursday 5 November
  • Sunday 15 November

These dates may change depending on progress and weather conditions. Diversion information will be issued in advance of each closure.
Further details about the inspection and repair work can be found on the NE Trunk Roads website:https://netrunkroads.scot/latest-news/a96-river-spey-bridge-fochabers-works-update/